Item | Decision and Action |
---|---|
1 | Conflicts of Interest N/A Previous minutes and actions Minutes and actions were accepted with minor edits recommended. Action -20202710-01: Secretariat to update September minutes as per recommendations |
2 | Strategy/Stakeholder 2.0 Strategy Execution Action -20202710-02: CEO to send a copy of ‘Strategy Execution’ presentation to Chair and Members. Action -20202710-03: DSNSW - prioritise schedule for dam risk reports. Matters for decision 2.1 Annual Report Action -20202710-04: Annual Report to be updated as per Member’s recommendations and sent for approval out of session. Action -20202710-05: Declared dams number to be consistent for annual report. Matters for discussion 2.2 Quarterly update – dams above safety threshold Action -20202710-06: Operations team to follow up on Hume Dam regarding risk assessment status. Matters for Noting 2.3 Levy update 2.4 Strategic Deep Dive – Progress update – Emergency Management Risk Action -20202710-07: DSNSW to investigate undertaking an emergency management exercise 2.5 Key Performance Indicators and Projects Action -20202710-08: Key performance indicators to include elements of Operations report. |
3 | Governance Matters for decision 3.1 O&M Plan guideline publication O&M plan guideline approved for publication |
4 | Operations Matters for decision 4.1 Declaration and De-declaration of dams Declarations and De-declarations approved by Members. Action -20202710-09: Operations team to check risk status of Oakey dam. 4.2 Taralga Dam update and declaration Declaration of Taralga Dam and its categorisation as a high B consequence category dam approved by Members. Action -20202710-10: DSNSW to develop document of key points regarding Taralga dam. Matters for Noting 4.3 CEO Report Action -20202710-11: ADKAR scores for CC of dam to be considered in future CEO report. Action -20202710-12: CEO to re-insert actuals in Finance summary as well as a nominal indication for projects. Action -20202710-13: For delegations: Significant changes to include a small summary in future meetings. 4.4 Support for regional town water infrastructur |
5 | General Business 5.1 November meeting (23-24) Members agreed to postpone the face to face November meeting until Covid19 restrictions have eased |
6 | Meeting Finalisation Members reviewed the actions taken and commended management on the success of the meeting. Meeting closed @ 1.00pm Next meeting: 24/11/2020. Remote |